February 6 Update
This week I met with representatives from the Township and the Owner’s Representative (Michael Baker International) for PennDOT to discuss the current status of the bridge replacement project. The construction team assured me that the closure scheduled for February 19 through 22 is on track to occur as scheduled. The next closing will occur in May, and, while there is a tentative date in place right now, this date is a bit harder to pin down given all of the activities that need to occur prior to the next closing.
The project involves close coordination between SEPTA, Aqua PA, and PECO, which adds complexity to the coordination on the project.